Cloud migration planning template

A simple way to list your applications, decide what to do with each one, and group them into migration waves you can actually deliver.

The Cydonia team

Most cloud migrations that run late do so for the same reason: the team didn’t know exactly what they were moving. An application turns out to depend on a file share nobody mentioned, or a database is shared by three systems instead of one.

This template fixes that by making you write everything down first. Copy the table into a spreadsheet and fill in one row per application or service.

Step 1: List everything

For each application, capture these columns:

Column What to write
Application The name your team uses for it
Owner The person who can answer questions about it
What it does One line, in business terms
Business impact if down High, medium or low
Users Internal, customers, partners
Depends on Databases, file shares, other apps, third-party services
Data size Rough size of its data (GB or TB)
Current hosting Where it runs today
Known problems Slow, fragile, out of support, hard to deploy
Approach See step 2
Wave See step 3

Don’t aim for perfect. A rough first pass in a day is more useful than a perfect one in a month. Fill gaps by talking to the owners.

Step 2: Choose an approach for each one

Every application gets one of five labels:

  • Retire. Nobody really uses it. Switch it off instead of moving it. Most inventories find a few of these.
  • Replace. A SaaS product now does the job better. Move the data and stop running it yourself.
  • Rehost. Move it as it is onto cloud servers. Fastest, but you keep the same problems.
  • Replatform. Make small changes so it can use managed services, such as moving its database to RDS or Cloud SQL, or running it in containers.
  • Refactor. Rework it properly to take advantage of the cloud. Most effort, most benefit. Save this for systems that matter and are changing anyway.

A common mistake is to refactor everything. Most applications should be rehosted or replatformed, with refactoring reserved for a few.

Step 3: Group into waves

A wave is a set of applications you move together over a few weeks. Good waves follow three rules:

  1. Start small and low-risk. The first wave should be one or two internal applications with few dependencies. Its real job is to test your process, tooling and runbooks.
  2. Move dependencies together. If two applications share a database, they go in the same wave, or the database moves first.
  3. Leave the most critical systems until you’ve practised. By the time you move customer-facing systems, the team should have done several migrations already.

Step 4: Write a runbook for each wave

For every wave, write down:

  • the steps to move, in order, with who does each one
  • how you’ll test that everything works afterwards
  • the point of no return, and how to roll back before it
  • who needs to be told, and when

Do a full rehearsal in a test environment before the real move.

Step 5: Track cost from the start

Set up cost reporting in your cloud account before the first wave, and tag every resource with its application name. That way you can see what each application costs to run, and you’ll spot over-sized servers early. Cloud costs that aren’t watched in the first three months are much harder to bring down later.

A worked example

Application Impact if down Depends on Approach Wave
Internal wiki Low File share Replace with SaaS 1
Reporting dashboard Medium Main database (read-only copy) Rehost 1
Customer portal High Main database, payments API Replatform 3
Main database High — Replatform to managed database 2
Legacy billing tool Medium Main database Retire, move to billing SaaS 2

These rows are an example only. Your own inventory will look different, and that’s the point of doing it.